Header Ads Widget

NextEra takes $800 mln charge for WV-VA Mountain Valley natgas pipe

nextera-natgas-pipe

NextEra Energy Inc (NEE.N) said one of its units recorded an $800 million impairment charge in the first quarter as the US renewable energy company re-evaluates its investment in the long-delayed Mountain Valley natural gas pipeline from West Virginia to Virginia.

NextEra said in a US Securities and Exchange Commission filing on Friday that its NextEra Energy Resources unit and other Mountain Valley joint venture partners continue to evaluate options and next steps for the project.

The US Court of Appeals for the Fourth Circuit over the last month has invalidated key permits for the project issued by the US Fish and Wildlife Service and the US Forest Service.

The court rulings were the latest setback for the pipeline, which is years behind schedule and billions of dollars over budget.

Several analysts have said the court decisions would likely delay the project startup until 2023 or 2024. Before the latest setbacks, Equitrans Midstream Corp (ETRN.N), the project’s lead partner, said it expected the pipeline to cost about $6.2 billion and enter service in the summer of 2022.

Equitrans said in January it was “evaluating the project’s next steps and timing considerations,” noting total work on the pipeline was “nearly 94% complete.”

Mountain Valley is one of several US pipeline projects delayed by regulatory and legal fights with environmental and local groups which found problems with federal permits issued during President Donald Trump’s administration.

When Mountain Valley construction started in February 2018, Equitrans estimated the 303-mile (488-km), 2-billion-cubic-feet-per-day (bcfd) project would cost about $3.5 billion and enter service by late 2018.

Equitrans has a 47.8% ownership interest in Mountain Valley and will operate the pipeline.



from Business News updates - Latest news stories on Economy from Pakistan https://ift.tt/nz5KeVL

Post a Comment

0 Comments